Contract Lifting
Project Overview
Skanska called in Fortis Heavy Lift Group to remove internal construction hoists and their base units from a project in central London. The hoists stood inside the building, where a conventional crane could not reach.
Fortis brought in a UNIC URW 506 mini crane with an expert A66-qualified operator. The team lifted out the hoist cars and base units and lowered them through the building, completing the job in a single day.
The Challenge
The hoists had done their job, and now they had to come out of the building’s interior.
Several challenges had to be overcome:
- Hoists and base units located inside the building
- No access for a mobile or tower crane
- Heavy hoist cars lifted out and lowered through internal voids
- A live construction site, with the programme depending on a quick removal
The Solution
Mini cranes are small but very powerful. Fortis set up a UNIC URW 506 inside the building, on spreader pads to spread its outrigger loads.
The crane lifted each hoist car and base unit clear, then lowered it through the building’s internal void to the level below for removal. The A66 operator controlled each lift with the precision needed in a confined, steel-framed space.
Specialist Equipment
UNIC URW 506 mini crane
A compact spider crane with serious capacity, set up inside the building where nothing larger would fit.
A66-qualified operator
A specialist compact crane operator, experienced in tight internal lifts.
Outrigger spreader pads
Spread the crane’s loads safely across the slab.


Small crane. Big hoists. Done in a day.
All of the internal hoists and base units were removed in a single day, keeping Skanska’s programme on track.