Plant & Machine Movement
Project Overview
Fortis Heavy Lift Group successfully completed the first phase of a complex transformer installation project at the Rolls-Royce development in Portsmouth, delivering the safe offloading, transportation, rotation and final positioning of six 10-tonne transformers.
The project required a specialist heavy lifting and machinery moving solution due to significant overhead restrictions, limited manoeuvring space and exceptionally tight installation tolerances. Through detailed planning, specialist equipment and an experienced project team, Fortis successfully positioned each transformer within a precise 5mm tolerance while maintaining a flawless safety record.
The Challenge
The installation involved relocating six high-value transformers from delivery vehicles into their designated substation locations within the Rolls-Royce facility.
Several significant challenges had to be overcome:
- Severe height restrictions throughout the access route.
- Limited space for manoeuvring large electrical assets.
- The requirement to rotate each transformer by 90 degrees within confined areas.
- Precise positioning onto steel pit supports.
- Strict installation tolerances of just 5mm.
With each transformer weighing 10 tonnes, conventional handling methods were not suitable. A bespoke heavy lifting and load-moving strategy was required to ensure safe and accurate installation.
The Solution
Fortis developed a specialist low-profile handling solution designed specifically for the site constraints and installation requirements.
Using a combination of specialist lifting equipment and powered load-moving systems, the team safely transported each transformer through the restricted-access environment before carrying out complex positioning operations inside the substations.
The operation included precise directional changes, controlled 90-degree rotations and final installation onto steel support structures, all while working within exceptionally tight clearances.
Specialist Equipment
To achieve the required level of precision and control, Fortis deployed a range of specialist heavy lifting equipment, including:
Versa-Lift 40/60 forklift
The Versa-Lift 40/60 provided the ideal solution for handling heavy loads in low-headroom environments. Its compact design allowed the team to transport and position the transformers where larger conventional lifting equipment could not operate.
Powered load-moving systems
Ultra-low-profile powered skates were used to minimise overall operating height and allow smooth movement through restricted areas while maintaining full control of the load at all times.
Precision positioning systems
Specialist jacking and alignment techniques enabled the team to lower each transformer onto its steel pit supports and achieve the required 5mm installation tolerance.


Delivering millimetre-perfect results
One of the most technically demanding aspects of the project was the final positioning phase.
Each transformer required careful rotation and alignment before being lowered into its final location. Through meticulous planning and coordinated execution, the Fortis team achieved precise placement of every unit, ensuring compliance with the project’s engineering specifications and operational requirements.
The successful completion of Phase One has paved the way for the remaining transformers to be installed during the next stage of the project.