Project Overview
A specialist rehabilitation hospital in Leamington Spa asked Fortis Heavy Lift Group to lift, shift and install new air conditioning units in one of its buildings. The hospital cares for young adults recovering from acquired brain injuries, and the site stayed fully operational throughout.
The hospital’s managers set two clear rules: keep noise to an absolute minimum, and do not crane any equipment over buildings where patients were resting. Fortis delivered the job without a crane, using Porta-Gantries, jacks and skates.
The Challenge
Patients at the hospital were undergoing treatment that needed plenty of rest, so this had to be a quiet job on a live site.
Several challenges had to be overcome:
- Keeping noise to an absolute minimum throughout
- No crane lifts over buildings where patients were
- A live hospital site, with staff and patients moving around
- Getting the units from transport to their final position by hand-controlled methods
The Solution
Fortis carried out site surveys and meetings with the hospital team, then produced a plan to move every unit from transport to its final location without a crane.
The plan used Porta-Gantries with chain blocks to lift the units, then jacks and skates to move them quietly into place. It also set out the steps the team would take to keep noise down at every stage.
Specialist Equipment
Porta-Gantries with chain blocks
Lightweight aluminium gantries that lifted the units off transport and onto their bases with no engine noise.
Machine skates
Rolled each unit smoothly and quietly to its final position.
Hydraulic jacks
Controlled, low-noise lifting and lowering for the final set-down.


A lift and shift you could barely hear
Every air conditioning unit was moved from transport to its final location safely and on plan.
The hospital kept all of its therapies running, and patients were able to rest in peace while the work went on around them.