The Mary Rose Trust at Portsmouth Historic Dockyard asked Fortis Heavy Lift Group to relocate a cannon from the Mary Rose, along with other priceless artefacts, to a new display in the museum. Most loads can be replaced if the worst happens. These could not.
Fortis planned the move over several site meetings and carried it out in a single night, using Porta-Gantries, chain blocks, jacks, skates and scoots. The museum opened as normal the next morning.
The Challenge
This was a lift with no margin for error, inside a busy working museum.
Several challenges had to be overcome:
- Artefacts that are priceless and can never be replaced
- Absolutely no damage to any item
- Daytime work was unsafe and disruptive with so many visitors
- Only one night available to complete the move
The Solution
Fortis held numerous site meetings with the museum team to plan every step, so nothing would be left to chance on the night.
The move was scheduled overnight to keep the public well away and let the museum open on time. Our team used a Porta-Gantry with chain blocks to lift the cannon from its old display, then moved it on a timber cradle using jacks, skates and scoots, and lowered it gently onto its new plinth. Display cases were handled with the same care.
Specialist Equipment
Porta-Gantry with chain blocks
Fine, hand-controlled lifting of the cannon in a gallery with no room for a crane.
Machine jacks, skates and scoots
Smooth, low-level moves of heavy artefacts and display cases across finished museum floors.
One-night lift plan
A detailed, rehearsed sequence that fitted the whole move into a single night.


One night. No second chances.
Thanks to meticulous planning, the Fortis team completed the work in good time and the museum opened on schedule, exactly as promised.