Plant & Machine Movement
Project Overview
EPES appointed Fortis Heavy Lift Group to remove a 4-tonne transformer, a ring main unit (RMU) and LV switchgear from an internal substation at the University of East Anglia in Norwich. The plant sat deep inside a building under redevelopment, with poor ground, tight doorways and low ceilings along the route out.
Fortis delivered the work over two visits under full contracted lifting and handling. On the first, the team repositioned everything inside the substation. On the second, a Fortis-supplied telehandler carried each item out beneath the building’s concrete frame and loaded it onto transport.
The Challenge
The substation was never designed to have its plant taken back out.
Several challenges had to be overcome:
- A 4-tonne transformer sitting on a gravel base inside a tight substation room
- Very tight headroom and width at doorways and along the route out
- Poor ground on the access route, with excavations near the work area
- Low concrete soffits overhead, leaving little clearance for a laden telehandler
- A live redevelopment site, with other trades working all around
The Solution
Visit 1: repositioning. Fortis laid an interlocking multi-mat runway into the transformer room, flush with the door threshold, with 6 mm steel running plates on top. The transformer was jacked in tandem onto roller bars, slung around its base, and drawn forward across the plates with a pulling winch, then nudged into position with nail bars. The LV panels were raised and moved on scoots, and the RMU was jacked onto a pallet truck and taken to its storage point.
Visit 2: removal. With the travel route stoned and compacted, the telehandler drove in under banksman control. The team jacked the transformer onto timbers so the forks could pass right under its skid, fitted rubbers to stop it slipping, and ratchet-strapped it to the forks. The telehandler then carried it out beneath the building’s concrete frame and lowered it onto timbers on a handrailed lorry bed. The RMU and switchgear followed the same way.
Specialist Equipment
Telehandler
Supplied by Fortis to carry the 4-tonne transformer out beneath low concrete soffits and load it onto transport.
Multi-mat runway and steel running plates
A temporary runway over the gravel substation floor, so the transformer could be winched out on roller bars with minimal resistance.
Machine jacks, roller bars and scoots
Tandem jacking and low-level moves for the transformer, RMU and LV panels in a space with almost no room to spare.


Out of the substation, onto the lorry
The transformer, RMU and LV switchgear were all removed from the substation and loaded onto transport safely, with every move signed off by the client.
Splitting the job into an internal repositioning visit and a separate removal visit kept each stage simple and controlled, and fitted around the wider redevelopment programme.
On Site
Watch the transformer removal