Contract Lifting
Project Overview
Collins Demolition brought in Fortis Heavy Lift Group to remove a steel footbridge spanning the canal in Banbury, Oxfordshire. The bridge had to come out in one piece, lifted clear of the water and set down on the bank, without damaging the canal walls or the surrounding public realm.
Fortis delivered the job as a contract lift. A mobile crane set up on the canal side and, with a spreader beam rigged to the bridge deck, lifted the whole span out over the water and landed it safely on the bank.
The Challenge
Bridge removals leave no room for guesswork: the load is long, the radius is set by the water, and the public realm sits right alongside.
Several challenges had to be overcome:
- Lifting a long, flexible span in one piece without it twisting or sagging
- Working across open water, with the canal and towpath close by
- A town-centre setting, with paving, railings and street furniture to protect
- Setting the crane up on the canal side within safe ground-bearing limits
The Solution
Fortis planned the lift around the bridge’s lifting points, centre of gravity and the radius needed to clear the canal. The crane was set up on the canal side, with its outrigger loads checked against the ground conditions.
A spreader beam was rigged above the bridge deck with slings to the deck, so the span stayed level and evenly supported as it came off its bearings. Under the lift supervisor’s control, the crane raised the bridge clear, slewed it over the canal and lowered it onto the bank.
Specialist Equipment
Mobile crane
Set up on the canal side, with the capacity at radius to lift the full span over the water.
Spreader beam and slings
Kept the long, flexible span level and evenly loaded from lift-off to landing.
Full Contract Lift framework
Fortis owned the lift planning, RAMS and lift management, working alongside Collins Demolition on site.


One span, one lift, canal clear
The footbridge was lifted out in one piece and landed safely on the bank, leaving the canal clear and the surrounding area undamaged.
The whole operation was captured on time-lapse, from rigging the spreader beam to the empty canal.