Contract Lifting
Project Overview
Fortis Heavy Lift Group has an ongoing contract with several engineering companies to provide transport solutions and contract lifts across the UK. At Winscombe Water Recycling Centre on Max Mill Lane, near Bristol, Fortis collected water treatment plant from Dover and lifted it into its final position on site.
The loads included skid pumps, clean water backwash tanks and vessels. The route into site was extremely tight and crossed by high-voltage overhead power lines.
The Challenge
A rural water recycling site meant narrow lanes, tight turns and live power lines overhead.
Several challenges had to be overcome:
- An extremely tight access route into site
- High-voltage overhead power lines near the route and lift area
- Large tanks and vessels with challenging transport dimensions
- Turning circles and access for both the transport and the crane
The Solution
Fortis planned the job in depth. Transport dimensions and turning circles were checked against the route, and the access needed for the crane and lifting equipment was worked out in advance.
Fortis attended site and held meetings with every stakeholder before installation, so each hurdle was identified and solved before the day. Fortis then collected the plant from Dover, delivered it along the tight route and lifted each item into its final position.
Specialist Equipment
Mobile crane contract lift
Positioned to complete the lifts while staying clear of the overhead power lines.
Transport solutions
Fortis-managed collection from Dover and delivery to site, planned around the route’s turning circles.
Stakeholder planning
Pre-installation site meetings so every issue was solved before mobilisation.


No surprises on the day
Every skid pump, tank and vessel was delivered from Dover and installed in its final position safely.
Because every hurdle had been identified and overcome in advance, there were no issues on installation day.