Plant & Machine Movement
Project Overview
Fortis Heavy Lift Group partnered with international freight specialist Europa Showfreight to bring a printing press from continental Europe to a factory in Norfolk and install it. The press arrived in 25-tonne sections, which had to be offloaded, moved through a working factory and set down in position.
Fortis delivered a full plant movement and installation service, using a Versa Lift and a hydraulic gantry lift system to get each section from the trailer to its final position.
The Challenge
Getting a heavy print press from dock to destination meant solving problems on the road and inside the building.
Several challenges had to be overcome:
- Transporting heavy loads along Norfolk’s narrow country roads
- Several tight turns on the route into and through the factory
- Overhead obstructions along the move path
- Protecting the client’s other equipment in a live factory
- No margin for misalignment at the final position
The Solution
Fortis carried out several site inspections to survey the offload area and every route into the factory. That survey shaped the equipment choice and the move sequence.
A Versa Lift handled the 25-tonne sections through the tight turns and under the overhead obstructions. A hydraulic gantry lift system then gave the controlled lift and accurate positioning the press needed.
A specialist Fortis team worked alongside Europa Showfreight’s logistics team, so the handover from road transport to installation was seamless.
Specialist Equipment
Versa Lift
A heavy-capacity forklift-style machine that carried the press sections through tight turns and under low obstructions.
Hydraulic gantry lift system
Controlled, accurate lifting and placement of each 25-tonne section in a space with little room to spare.
Specialist plant movement team
Experienced riggers and lift supervisors who planned and ran the move from offload to final position.


Dock to destination, without a scratch
The move and installation went exactly to plan. The printing press was delivered and installed safely, on time and on budget, with no damage to the press or the factory.
Fortis continues to work closely with Europa Showfreight on a wide range of projects.