Plant & Machine Movement

Project Overview

Fortis Heavy Lift Group provided lifting and handling services to Overbury on the new BT development at 3 Snow Hill, Birmingham city centre. The task was to unload new switchgear and move it from the lower basement to its positions across four upper floors.

A three-person Fortis lift and shift team completed the work in two days, using specialist moving kit and full floor protection throughout.

  • Location: 3 Snow Hill, Birmingham city centre

  • Client: Overbury, for the BT development

  • Primary Assets: Switchgear panels, later CRAH units

  • Team: 3-person lift and shift crew

  • Duration: 2 days

  • Project Type: Plant movement and installation

  • Outcome: 3 further visits awarded

The Challenge

The building was nearly finished, so every move had to protect new finishes on every level.

Several challenges had to be overcome:

  • Finished floors on every level of the building
  • Tight service corridors, doorways and turns
  • Moving heavy panels from the lower basement up to four upper floors
  • Working around other trades on a busy fit-out site

The Solution

Fortis installed floor protection along every route before the switchgear arrived. That kept the new finishes safe from the first move to the last.

The team used a selection of lift and shift kit, including skates, pallet trucks and machine moving frames, to unload the switchgear and move each panel along the protected routes to its final position.

Careful planning and a compact, experienced crew meant the whole distribution was done in just two days.

Specialist Equipment

Machine skates and moving frames

Low-profile kit for rolling heavy switchgear panels through tight corridors and doorways.

Powered pallet trucks

Controlled moves of wrapped panels across the basement and onto the vertical route.

Temporary floor protection

Boards and mats laid before arrival, so no finished floor was marked.

Switchgear panel manoeuvred along a protected service corridor at 3 Snow Hill
Fortis operative with a powered pallet truck and wrapped switchgear in the basement

Two days. Four floors. Zero damage.

All of the switchgear was unloaded and moved from the lower basement to its positions across four upper floors in two days, with no damage to the building.

The client was so impressed with the speed and accuracy of the work that Fortis was asked back three more times to move CRAH units and other equipment from the basement to the upper levels.

Project gallery

More from the job

City crane outrigger on a spreader pad beside a Birmingham apartment development

Wrapped switchgear section on a moving frame beside installed panels in a Birmingham plant room

City crane outrigger on a spreader pad beside a Birmingham apartment development

Lift and shift team moving equipment through a doorway over floor protection boards

New switchgear panels installed in the switch room at 3 Snow Hill, Birmingham

Protected routes. Precise moves. Repeat business.

Why choose Fortis for switchgear and plant room moves?

Moving switchgear and critical plant through a finished building takes planning, protection and the right kit. Fortis surveys the route, protects the building and moves your equipment safely into position. Need plant moved in a live or newly fitted building? Contact Fortis Heavy Lift Group today.

Operator steering a transformer on a power load moving system along a corridor by remote

Equipment spotlight

Power load moving systems

Our remote-controlled power load moving systems drive heavy plant across floors, through doorways and into lifts with millimetre control, with no pushing, no pulling and fewer people near the load. They’re the safest way to move transformers, switchgear and machinery inside a building.

Lifting Excellence in Action

Explore our latest projects and achievements.