Project Overview
Fortis Heavy Lift Group delivered a complex, multi-phase plant replacement at the Mitchells & Butlers headquarters on Fleet Street, central Birmingham. The scope covered decommissioning and replacing two 5-tonne chillers, alongside a full PV solar panel load-out and scaffolding integration.
After months of engineering and planning, Fortis ran the job as a Full Contract Lift. A 7-axle Spierings mobile tower crane handled every lift from a single set-up, under a full council-approved road closure.
The Challenge
The project packed multiple heavy lifts and mixed materials into a tight, busy city-centre site.
Several significant challenges had to be overcome:
- Restricted space on Fleet Street for crane set-up
- Strict weight distribution and overhead considerations
- Extracting old chillers and installing new ones at high level
- Feeding scaffolding and delicate PV panels to the roof
- Public safety during operations in a live street
With a road closure in place, there was zero margin for logistical delay.
The Solution
Months of pre-planning let Fortis engineer a single, seamless workflow. All risk assessments and method statements were managed in-house.
Fortis selected a 7-axle Spierings mobile tower crane for its vertical and horizontal reach. From one set-up position, it overreached the building to handle both chiller swaps and the PV panel distribution.
A full road closure and diversion scheme on Fleet Street kept the public safe throughout.
Specialist Equipment
To manage multiple lifts safely in a tight urban radius, Fortis deployed:
7-axle Spierings mobile tower crane
The Spierings combined tower-crane reach with mobile-crane set-up, overreaching the building footprint from one position.
Urban traffic management
A council-approved road closure and diversion on Fleet Street protected the public during all crane operations.
Full Contract Lift framework
Fortis owned the planning, RAMS and lift management, coordinating chillers, scaffolding and PV panels in one schedule.


Two chillers, one crane position, zero delays
The old chillers came out and two new 5-tonne units went in at high level.
In the same operation, scaffolding components and PV solar infrastructure were fed safely to the roof. Every lift ran from a single, optimised crane position.
By managing permits, closures and the multi-asset lift schedule together, Fortis brought this high-profile project to a safe, on-time finish.